C343 · NSECH, Cramlington
Substantiation
Demo dataBuild the evidence pack for a variation or early warning from records that already exist on the project.
Evidence is linked, never copied. Removing a link here never deletes the original site record.
C343-VO-001
Concrete breakout to pile cap excavation
Evidence: WeakOpen case
Linked evidence
7
Key evidence
2
Outstanding
5
Complete
0
Evidence linked to this case
- KeySite Diary — 03/07/2026Site Diary · added by Sarah Johnson (You)
- Site Diary — 02/07/2026Site Diary · added by Sarah Johnson (You)
- KeyPile cap detail drawing (current revision)Drawing · added by Sarah Johnson (You)
- 5 photographs — 03/07/2026Photograph · added by Sarah Johnson (You)
- Jack Coates — Machine Operator (labour present)Labour · added by Sarah Johnson (You)
- HB-22T-360 — 22t excavator on sitePlant · added by Sarah Johnson (You)
- Shanco Delivery Programme R07Programme · added by Sarah Johnson (You)
What is missing
- RequestedClient instruction confirmation (demo requirement)Instruction · Sarah Johnson (You) · due 24/07/2026
- MissingMeasured quantity of concrete broken outQuantity · Callum Wright
- MissingCommercial quantity check against drawing C01Quantity
- MissingRelevant supplier / disposal cost evidenceCostCost and invoice records connect in a later module.
- MissingProgramme impact confirmationProgramme · Callum Wright
Cost records, invoices and correspondence are integration-ready sources. They are shown as gaps in this prototype rather than being invented.
Link existing project evidence
- Site Diary — 17/07/2026Callum, Phil, Ollie, Jack, Stefan and James on site. Continued duct install to plot boundary and setting out for MH07 base.
- Site Diary — 16/07/2026Mesh fixing to L02 slab bay 3. Rain from 14:00 stopped concrete pour to bay 4 — rescheduled.
- Site Diary — 15/07/2026Poured 45m³ CEM I to L02 bay 2. Setting out for MH07. Duct crew mobilised.
- Site Diary — 14/07/2026Continued excavation to Zone C. Delivery of 150mm PVC twinwall duct received and offloaded.
- Site Diary — 11/07/2026Gas membrane installed to plots 4–6. Toolbox talk delivered on hand digging near services.
- Site Diary — 10/07/2026Weekly plant inspections (bowser, SH92 dumper, SHRL21 laser). Continued kerb line to south elevation.
- Site Diary — 09/07/2026Restricted work due to weather. Housekeeping and drainage clearing in compound.
- Site Diary — 08/07/2026Setting out for MH06. Rebar fixed for pile caps PC12–PC15.
- Site Diary — 07/07/2026Concrete pour to pile caps PC08–PC11. Delivery of CEM I from Marsden Quarry.
- Site Diary — 04/07/2026Duct route surveyed by Callum with CAT4+ (SCA26). Marked out and permits issued.
- Site Diary — 03/07/2026Pile cap excavation continued. 22ton 360 (hubbway) worked northern boundary.
- Site Diary — 02/07/2026Deep drainage to run D3 completed to MH05. Backfill and compaction to line.
Commercial records and values shown here are illustrative prototype data. Linked project source records are existing Shanco OS project records.