C343 · NSECH, Cramlington

Substantiation

Demo data

Build the evidence pack for a variation or early warning from records that already exist on the project.

Evidence is linked, never copied. Removing a link here never deletes the original site record.
C343-VO-001

Concrete breakout to pile cap excavation

Evidence: WeakOpen case
Linked evidence
7
Key evidence
2
Outstanding
5
Complete
0

Evidence linked to this case

  • Site Diary — 03/07/2026
    Site Diary · added by Sarah Johnson (You)
    Key
  • Site Diary — 02/07/2026
    Site Diary · added by Sarah Johnson (You)
  • Pile cap detail drawing (current revision)
    Drawing · added by Sarah Johnson (You)
    Key
  • 5 photographs — 03/07/2026
    Photograph · added by Sarah Johnson (You)
  • Jack Coates — Machine Operator (labour present)
    Labour · added by Sarah Johnson (You)
  • HB-22T-360 — 22t excavator on site
    Plant · added by Sarah Johnson (You)
  • Shanco Delivery Programme R07
    Programme · added by Sarah Johnson (You)

What is missing

  • Client instruction confirmation (demo requirement)
    Instruction · Sarah Johnson (You) · due 24/07/2026
    Requested
  • Measured quantity of concrete broken out
    Quantity · Callum Wright
    Missing
  • Commercial quantity check against drawing C01
    Quantity
    Missing
  • Relevant supplier / disposal cost evidence
    Cost
    Cost and invoice records connect in a later module.
    Missing
  • Programme impact confirmation
    Programme · Callum Wright
    Missing

Cost records, invoices and correspondence are integration-ready sources. They are shown as gaps in this prototype rather than being invented.

Link existing project evidence

  • Site Diary — 17/07/2026
    Callum, Phil, Ollie, Jack, Stefan and James on site. Continued duct install to plot boundary and setting out for MH07 base.
  • Site Diary — 16/07/2026
    Mesh fixing to L02 slab bay 3. Rain from 14:00 stopped concrete pour to bay 4 — rescheduled.
  • Site Diary — 15/07/2026
    Poured 45m³ CEM I to L02 bay 2. Setting out for MH07. Duct crew mobilised.
  • Site Diary — 14/07/2026
    Continued excavation to Zone C. Delivery of 150mm PVC twinwall duct received and offloaded.
  • Site Diary — 11/07/2026
    Gas membrane installed to plots 4–6. Toolbox talk delivered on hand digging near services.
  • Site Diary — 10/07/2026
    Weekly plant inspections (bowser, SH92 dumper, SHRL21 laser). Continued kerb line to south elevation.
  • Site Diary — 09/07/2026
    Restricted work due to weather. Housekeeping and drainage clearing in compound.
  • Site Diary — 08/07/2026
    Setting out for MH06. Rebar fixed for pile caps PC12–PC15.
  • Site Diary — 07/07/2026
    Concrete pour to pile caps PC08–PC11. Delivery of CEM I from Marsden Quarry.
  • Site Diary — 04/07/2026
    Duct route surveyed by Callum with CAT4+ (SCA26). Marked out and permits issued.
  • Site Diary — 03/07/2026
    Pile cap excavation continued. 22ton 360 (hubbway) worked northern boundary.
  • Site Diary — 02/07/2026
    Deep drainage to run D3 completed to MH05. Backfill and compaction to line.

Commercial records and values shown here are illustrative prototype data. Linked project source records are existing Shanco OS project records.