C343 · NSECH, Cramlington

Site Diary

Demo data

Capture the day by form or by voice-interactive interview. Attach photos taken on this device.

Diary consistency — last 30 working days
12/30 completed40% · Poor
Mon, 10 Aug 2026
Completed Missed
Tue, 30 Jun 2026
Diary entry

09/07/2026

Submitted 09/07/2026 17:00 by Callum Wright
Rain
View Labour Summary

Conditions & staffing

Weather AM
Rain
Weather PM
Overcast
Temp (°C)
16
Wind (mph)
18
Shanco staff
4
Guest staff
0
Photos
3
Visitors

Narrative

Work description

Restricted work due to weather. Housekeeping and drainage clearing in compound.

Instructions received

Potential variations

Delays / disruption

AM rain — pour deferred.

Incidents / near-misses

Photos (3)

Commercial & contractual

  • Restricted working — AM rain, concrete pour deferred
    Needs ReviewC343-CE-001
    CostTimeProductivity1 early warning

Attachments

No additional files on this entry.