C343 · NSECH, Cramlington
Site Diary
Demo dataCapture the day by form or by voice-interactive interview. Attach photos taken on this device.
Diary consistency — last 30 working days
12/30 completed40% · Poor
Mon, 10 Aug 2026
Completed Missed
Tue, 30 Jun 2026Diary entry
16/07/2026
Submitted 16/07/2026 17:45 by Callum Wright
Overcast
View Labour SummaryConditions & staffing
- Weather AM
- Overcast
- Weather PM
- Rain
- Temp (°C)
- 17
- Wind (mph)
- 12
- Shanco staff
- 6
- Guest staff
- 2
- Photos
- 8
- Visitors
- McAvoy PM walk-round (10:30)
Narrative
Work description
Mesh fixing to L02 slab bay 3. Rain from 14:00 stopped concrete pour to bay 4 — rescheduled.
Instructions received
—
Potential variations
—
Delays / disruption
Rain — 2hrs lost on pour.
Incidents / near-misses
—
Photos (8)
Commercial & contractual
Nothing from this day has been flagged for commercial review. If something here carries a cost, time or scope consequence, report it and the QS will decide what it becomes.
Attachments
No additional files on this entry.