C343 · NSECH, Cramlington

Site Diary

Demo data

Capture the day by form or by voice-interactive interview. Attach photos taken on this device.

Diary consistency — last 30 working days
0/30 completed0% · Poor
Thu, 08 Oct 2026
Completed Missed
Fri, 28 Aug 2026
Diary entry

16/07/2026

Submitted 16/07/2026 17:45 by Callum Wright
Overcast
View Labour Summary

Conditions & staffing

Weather AM
Overcast
Weather PM
Rain
Temp (°C)
17
Wind (mph)
12
Shanco staff
6
Guest staff
2
Photos
8
Visitors
McAvoy PM walk-round (10:30)

Narrative

Work description

Mesh fixing to L02 slab bay 3. Rain from 14:00 stopped concrete pour to bay 4 — rescheduled.

Instructions received

—

Potential variations

—

Delays / disruption

Rain — 2hrs lost on pour.

Incidents / near-misses

—

Photos (8)

Commercial & contractual

Nothing from this day has been flagged for commercial review. If something here carries a cost, time or scope consequence, report it and the QS will decide what it becomes.

Attachments

No additional files on this entry.