C343 · Cramlington
C343 — NSECH, Cramlington
Demo dataSelected-project view for delivery, documents, commercial management and costs.
Project navigation = everything for one live job.
Client
McAvoy Group
Contract Value
£2.45m
Stage
Delivery
End Date
18/12/2026
Recent Project Activity
- Site diary submitted — 17/07/2026Link corridor foundations poured · 10 photosCallum Wright01/01/1970
- Drawing 010221-DSR-06-00-DR-E-6134 issuedSite Plan HV Cable Layout — C02McAvoy Design01/01/1970
- Third Party Gas Membrane Sign Off uploadedGeoShield A2 B2 – A15 B15Jonathan Bradley31/12/1969
- TARMAC Concrete — CEM I mix approvedMix design uploaded to O&MPaul Deery31/12/1969
- Slab Pour 2 as-built uploadedTOC, Stone, Insulation, RC — 4 sheetsCallum Wright31/12/1969
Document Centre Shortcuts
Project Health
- ProgrammeOn track
- BudgetOn track
- Cost PerformanceWatch
- QualityOn track
- SafetyOn track
- RisksWatch
- ResourcesOn track